The manual butterfly valve of cement can adjust the opening according to the batching time. In the continuous batching and weighing test, the selected weighing advance should be adjusted and recorded to ensure accurate batching accuracy in the shortest time.
First start the thick oil pump to fill the mixer bearing, the mixer idle test: confirm that there is no foreign matter in the twin-shaft mixer.
Restart the mixer motor for 30 minutes, confirm that the operation is normal, the gap between the blade and the mixing drum wall is adjusted to <3mm. See the mixer instruction manual. Check that there is no foreign matter in the screw conveyor, start the screw conveyor one by one, and run for 15 minutes without abnormality.
Start the belt conveyor. When the feeder starts running, the tape should not be deflected. If there is a deviation, the tail tension bolt and the centering roller can be adjusted. There was no abnormality after 15 minutes of operation.
No-load linkage test: The microcomputer manually and automatically performs the no-load linkage test of the mixing station system to verify whether the equipment startup sequence is correct and whether the equipment and mechanism are operating normally. After the adjustment is completed, all machines should be subjected to an 8-hour no-load linkage running test.