How To Install The Main Components Of Concrete Mixing Plant?

Date:2020-06-01     Label:

concrete mixing plant

stabilized soil mixing station

Medium concrete mixer


1. Installation of mixing host and powder batching system.

Lift the concrete mixing plant mainframe, place it on the foundation, and fasten its anchor bolts. The installation of the finished product storage hopper of the concrete mixing plant suspends the finished product storage hopper, erects the outriggers, and connects the walking platform, ladder and finished product storage hopper. For the installation of the concrete batching machine, lift the concrete batching machine on its base, connect the plug-in board, put the heightened plates on both sides away and connect the plug-in board, and then unfold the original aggregate conveyor to move the front and back Connect the frame, align the electric drum with the center of the mixer hood hole, and finally tighten the anchor bolts.

How To Install The Main Components Of Concrete Mixing Plant?

2. Installation of concrete mixing plant cement warehouse for material storage equipment.

Assemble the components of the cement silo one by one on the ground, lift the cement silo, and place the side of the lower silo body support to the powder batching system, fix the upper and lower silo bodies, and then fix the anchor bolts. The installation of the screw conveyor of the concrete mixing station, hoist the screw conveyor, connect the screw conveyor ball hinge with the cement hopper outlet, make the outlet align with the powder hopper inlet, and then use the steel wire rope to connect the conveyor and cement Connect the lifting ears of the warehouse, and then fix the anchor bolts. The concrete mixing station hangs the water pump and puts it in a proper position, and connects the output water pipe. Install the air compressor, place the air compressor on the side of the finished hopper, connect the air compressor outlet to the air control box inlet with a gas pipe, and connect the air control box outlet to the air pipe of the cement silo.

3. Installation of concrete mixing plant belt conveyor for finished materials.

Unfold the finished belt conveyor from the bend, place the rear frame on its base, connect the front and rear frames, then connect the front and rear legs to the conveyor, and connect the diagonal brace to the lifting ears on the frame Then, lift the front of the conveyor, connect the front and rear legs and the diagonal brace, and then fasten the anchor bolts of the front and rear legs.

Please send us a message

Contact Us

Tel/Wechat/Whatsapp:+86-18660761375

Email:sales@chinacoalintl.com

Fix: +86-537-2350961

Address:No. 11, North of Kaiyuan Road, High-tech Zone, Jining City, Shandong Province, China

+

+

Please leave a message
skype
message