1. Before starting the machine, please check a series of accessories of the concrete mixing plant, including butter and oil. At the same time check the water valve, water pump, pump and water supply, air compressor, storage bin door, unloading belt open, mixing and host open The supply belt opens the ingredients (including pellets, cement)-opens the water supply, etc. This is the operation before the concrete mixing plant starts operation.
2. The switching sequence at the beginning of the concrete mixing plant. Ingredients (including particles and cement) are shut off from the water supply system, unloaded (no belt storage), the mixing main engine is shut off (not stored in the mixing box), unloaded belt (belt is not stored), the storage box door is closed, the air compressor is cleaned The shut-off valve of the compressor stirs the tank and shuts off the main power supply.
The order of these operations is particularly important. For example, if the operation is not correct, the material is mixed in the mixer. When the machine is turned off, the concrete will be blocked in the mixer.
3. The concrete mixing plant operators must go through learning and training to understand the structural performance and operating procedures of the equipment mixing system, be familiar with safe operations and technical specifications, basic computer operations, basic understanding of quality requirements and the main performance of raw materials And specifications, functions, only after the actual evaluation of the superior company can go to work.