How To Control Dust In Concrete Mixing Plant?

Date:2020-02-15     Label:

Concrete Mixing Plant

concrete mixing station

concrete mixer

Promote the advancement and transformation of commercial concrete mixing plant, complete the coordinated development of commercial concrete production, urban construction, and environmental protection, and conduct special inspections on the dust treatment of ready-mixed concrete mixing stations.

The inspection plan included the city's talented ready-mixed concrete mixing plant. There are 10 aspects to check:

1. Whether the implementation of the dust rectification treatment responsibility of the mixing station is performed, is it the part of the responsibility for performing the dust rectification, the person in charge;

2. Whether the construction of the fence around the site has a continuous closed fence.

How To Control Dust In Concrete Mixing Plant?

3. Whether the distance, working area and yard are hardened, whether the distance, working area and yard are hardened.

4. Aggregate yard and batching silo are closed. Is the aggregate yard and batching silo sealed? Is spraying dust reduction method used?

5. Equipped with vehicle scouring equipment and in and out scouring conditions, is it equipped with vehicle scouring equipment at the entrance of the field area, and vehicles in and out of the area actively scour.

6. Whether the site arranges drainage and sewage treatment, does it have an arranged drainage system; does it have a level 3 sedimentation tank, and does it have sewage treatment?

7. Useful separation between working area, living area and production area. Is the working area, living area and production area separated?

8. The performance of the production line's dust removal and suppression methods. Is the second floor or more of the mixing building closed, is the silo closed, is the equipment silo bag dust removal and other equipment, is the conveyor belt closed, and the inlet is closed?

9. GPS equipment of the mixer truck, extension of license plate number and anti-drip equipment, is the vehicle owned by the equipment GPS, receiving hopper, extended license plate number; is the appearance of the mixer truck is regular.

10. concrete mixing plant does the dust removal and cleaning of the distance and place be performed by the cleaning staff and cleaning methods? Is the place and distance cleaned on time, sprinkled with water, washed, is the sand and stones piled up, is it equipped with a sprinkler and sprinkled water on time to reduce dust?

Please send us a message

Contact Us

Tel/Wechat/Whatsapp:+86-18660761375

Email:inquiry@chinacoalintl.com

Fix: +86-15376502861

Address:No. 11, North of Kaiyuan Road, High-tech Zone, Jining City, Shandong Province, China

+

+

Please leave a message
skype
message